MH10 Dolphingstone

Musselburgh, East Lothian

ConsentedHigh confidence

Homes

621

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

621

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Position
Geocoded from the site name

Planning

Reference
15/00537/PPM
Decision
PPM
Dated
3 December 2020
Audit reference
E494
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at MH10 Dolphingstone
YearHomes
2026/2718
2027/2870
2028/2980
2029/3080
2030/3190
2031/3290
2032/3390
2033/3490
2034/3513
Programmed in total621

Where this comes from

East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.

Buying into one of these, letting near one, or weighing the return.

A new estate in Musselburgh brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.