MH10 Dolphingstone

Musselburgh, East Lothian

ConsentedHigh confidence

Homes

621

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

621

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Position
Geocoded from the site name

Planning

Reference
15/00537/PPM
Decision
PPM
Dated
3 December 2020
Audit reference
E494
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at MH10 Dolphingstone
YearHomes
2026/2718
2027/2870
2028/2980
2029/3080
2030/3190
2031/3290
2032/3390
2033/3490
2034/3513
Programmed in total621

Where this comes from

East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.