Building now · Edinburgh

Maybury Central - Plots 2/3

Edinburgh

Under constructionHigh confidence

Homes

269

Counted in the audit's total

Built so far

66

At the audit's base date, 31 March 2025

Still to build

203

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Builder
Barratt Homes / West Craigs
Tenure
Market
Mix
210 houses, 59 flats
Site area
7.61 ha
Address
Maybury, Edinburgh

Planning

Reference
21/03986/AMC
Decision
Approval of matters specified in conditions
Dated
14 December 2021
Audit reference
5246.2.5
Plan reference
HSG 19: Maybury Central - Plots 2/3
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Maybury Central - Plots 2/3
YearHomes
2025/2639
2026/2768
2027/2830
2028/2930
2029/3030
2030/316
Programmed in total203

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.