Skip to content

Edinburgh and the Lothians.

Building now · Edinburgh

Maybury Central - Plot 9

Almond, Edinburgh

Under constructionHigh confidence

Homes

122

Counted in the audit's total

Built so far

29

At the audit's base date, 31 March 2025

Still to build

93

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
Market
Mix
51 houses, 71 flats
Site area
58.82 ha
Address
Maybury, Edinburgh

Planning

Reference
22/05308/AMC
Decision
Approval of matters specified in conditions
Dated
10 February 2023
Audit reference
5246.2.9
Plan reference
HSG 19: Maybury Central - Plot 9
Audit base date
31 March 2025

What the application says

Erection of 122 dwellings, associated drainage, infrastructure and landscaping (in respect of conditions 5 (Part 2 i, ii, iii, iv, v, vi), 6(a), 6(b), 6(c), 6(d), 6(e), 6(f), 6(g), 6(h), 6(i), 6(j), 6(k(i-ix)) & 10 of consent 16/04738/PPP for Plot 9.

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Maybury Central - Plot 9
YearHomes
2025/2650
2026/2743
Programmed in total93

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.

Buying into one of these, letting near one, or weighing the return.

A new estate in Almond brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.