Under constructionHigh confidence

Homes

136

Counted in the audit's total

Built so far

40

At the audit's base date, 31 March 2025

Still to build

96

council audit figure

Affordable

136

Within the total

Where it is

The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
Affordable
Mix
136 flats
Site area
3.24 ha
Address
Regeneration Masterplan, Pennywell Road

Planning

Reference
17/04190/AMC
Decision
Approval of matters specified in conditions
Dated
18 December 2017
Audit reference
5159.2
Audit base date
31 March 2025

What the application says

Approval of Matters Specified in Conditions of Application No. 17/00314/PPP relating to Phase 2 (Block 1) and Phase 3 (Block 3) of the Pennywell Muirhouse Civic Centre - Phased mixed use development comprising a total of 136 dwellings, shops and food & drink uses, landscaping, open space, access, drainage and other associated development.

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Regeneration Masterplan, Pennywell Road
YearHomes
2025/2636
2026/2760
Programmed in total96

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.

Buying into one of these, letting near one, or weighing the return.

A new estate in Almond brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.