Skip to content

Approved, not started · Edinburgh

Orchard Brae

Edinburgh

ConsentedHigh confidence

Homes

151

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

151

council audit figure

Affordable

65

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
Mixed
Site area
0.78 ha
Address
10 Orchard Brae, Edinburgh

Planning

Reference
21/06512/FUL
Decision
Full planning permission
Dated
7 September 2023
Audit reference
6658
Plan reference
H34: Orchard Brae
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Orchard Brae
YearHomes
2026/2721
2027/2850
2028/2980
Programmed in total151

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.