Approved, not started · Edinburgh

No. 26 Cleikiminrig

Edinburgh

ConsentedHigh confidence

Homes

260

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

260

council audit figure

Affordable

65

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Builder
E&A Partnerships Ltd & Niddrie Develop
Tenure
Mixed
Mix
130 houses, 130 flats
Site area
6.39 ha
Address
Land south of No. 26 Cleikiminrig

Planning

Reference
22/03291/PPP
Decision
Planning permission in principle
Dated
31 August 2023
Audit reference
6666
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at No. 26 Cleikiminrig
YearHomes
2027/2830
2028/2930
2029/3030
2030/3130
2031/3230
2032/3330
2033/3430
2034/3530
2035+20
Programmed in total260

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.