Building now · Edinburgh
Leith Walk / Manderston Street
Edinburgh
Homes
54
Counted in the audit's total
Built so far
0
At the audit's base date, 31 March 2025
Still to build
54
council audit figure
Affordable
27
Within the total
Where it is
The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.
- Open in the atlas
- Google Maps
- OpenStreetMap
- 55.96804, -3.17307
About the site
- Builder
- CW Properties, Cambay, And CA Ventures
- Tenure
- Mixed
- Mix
- 54 flats
- Site area
- 0.98 ha
- Address
- Leith Walk/Manderston Street, Edinburgh
Planning
- Reference
- 22/01563/FUL
- Decision
- Full planning permission
- Dated
- 18 January 2024
- Audit reference
- 6664.1
- Plan reference
- H42: Leith Walk/Manderston Street
- Audit base date
- 31 March 2025
Homes expected each year
The council’s own build-out programme. The first year is the current audit year.
| Year | Homes |
|---|---|
| 2025/26 | 25 |
| 2026/27 | 29 |
| Programmed in total | 54 |
Where this comes from
City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.
- Open the source record (edinburgh.gov.uk)