Building now · Edinburgh
Gayfield Square
Edinburgh
Homes
11
Counted in the audit's total
Built so far
0
At the audit's base date, 31 March 2025
Still to build
11
council audit figure
Affordable
0
Within the total
Where it is
The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.
- Open in the atlas
- Google Maps
- OpenStreetMap
- 55.95941, -3.18667
About the site
- Builder
- Mactaggart & Mickel
- Tenure
- Market
- Mix
- 11 flats
- Site area
- 0.05 ha
- Address
- 11 Gayfield Square
Planning
- Reference
- 17/03392/FUL
- Decision
- Full planning permission
- Dated
- 29 November 2021
- Audit reference
- 4946
- Audit base date
- 31 March 2025
Homes expected each year
The council’s own build-out programme. The first year is the current audit year.
| Year | Homes |
|---|---|
| 2026/27 | 11 |
| Programmed in total | 11 |
Where this comes from
City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.
- Open the source record (edinburgh.gov.uk)
Buying into one of these, letting near one, or weighing the return.
A new estate in Edinburgh brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.