Approved, not started · Edinburgh

Clovenstone House

Edinburgh

ConsentedHigh confidence

Homes

97

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

97

council audit figure

Affordable

34

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
Mixed
Site area
0.68 ha
Address
Clovenstone House, Edinburgh

Planning

Audit reference
6808
Plan reference
H83: Clovenstone House
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Clovenstone House
YearHomes
2029/3047
2030/3150
Programmed in total97

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.