Approved, not started · Edinburgh

Bridge Street

Edinburgh

ConsentedHigh confidence

Homes

6

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

6

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Builder
McTaggart Properties Ltd
Tenure
Market
Mix
4 houses, 2 flats
Site area
0.16 ha
Address
Bridge Street

Planning

Reference
23/01160/FUL
Decision
Full planning permission
Dated
5 January 2024
Audit reference
6679
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Bridge Street
YearHomes
2027/282
2028/294
Programmed in total6

Where this comes from

City of Edinburgh Council Housing Land Audit 2025. In City of Edinburgh Council Housing Land Audit 2025, base date 31 March 2025.