Barbachlaw Farm, Salters Road (Wallace Park) Phase 1
Musselburgh, East Lothian · EH21 8QH
Homes
33
Counted in the audit's total
Built so far
21
At the audit's base date, 31 March 2025
Still to build
12
council audit figure
Affordable
0
Within the total
Where it is
The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.
- Open in the atlas
- Google Maps
- OpenStreetMap
- 55.93418, -3.02121
About the site
- Builder
- Ambassador Homes
- Mix
- 33 houses
- Position
- Matched to the planning register by reference
Planning
- Reference
- 22/00075/P
- Decision
- Detailed planning permission
- Dated
- 5 October 2022
- Audit reference
- E469a
- Audit base date
- 31 March 2025
Homes expected each year
The council’s own build-out programme. The first year is the current audit year.
| Year | Homes |
|---|---|
| 2025/26 | 6 |
| 2026/27 | 6 |
| Programmed in total | 12 |
Where this comes from
East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.
- Open the source record (eastlothian.gov.uk)
- Also appears in East Lothian planning register as 22/00075/P, consented, 33 homes (pa.eastlothian.gov.uk)
Buying into one of these, letting near one, or weighing the return.
A new estate in Musselburgh brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.