Skip to content

Building now · East Lothian

Barbachlaw Farm, Salters Road (Wallace Park) Phase 1

Musselburgh, East Lothian · EH21 8QH

Under constructionHigh confidence

Homes

33

Counted in the audit's total

Built so far

21

At the audit's base date, 31 March 2025

Still to build

12

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Mix
33 houses
Position
Matched to the planning register by reference

Planning

Reference
22/00075/P
Decision
Detailed planning permission
Dated
5 October 2022
Audit reference
E469a
Audit base date
31 March 2025

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Barbachlaw Farm, Salters Road (Wallace Park) Phase 1
YearHomes
2025/266
2026/276
Programmed in total12

Where this comes from

East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.

A home to sell before you buy?

A move to a new home in Musselburgh starts with the one you own now: what it would sell for, or what it would let for if you kept it. Enter its postcode and the figure is on your screen.

Both are free and instant on screen. No email needed to see the number.