Approved, not started · West Lothian

Willowdean (Site B)

Bridgend, West Lothian · EH49 (Bridgend village)

ConsentedHigh confidence

Homes

98

Counted in the audit's total

Built so far

0

At the audit's base date, 31 March 2025

Still to build

98

council audit figure

Affordable

25

Within the total

Where it is

The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
private
Site area
6.20 ha

Planning

Reference
1032/PAC/18; 1193/PAC/21; 0930/PAC/22; 0418/PAC/23; 0384/FUL/24
Decision
Full
Audit reference
127
Plan reference
H-BD 2
Audit base date
31 March 2025

What the application says

Erection of 98 houses, formation of site accesses, roads/footpaths, site regrading works, SUDs pond, open space, landscaping, and other associated works

Notes

Housing Land Audit 2024, combined phases.

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Willowdean (Site B)
YearHomes
2028/2949
2029/3024
2030/3125
Programmed in total98

Where this comes from

West Lothian HLA 2025. In West Lothian Council Housing Land Audit 2025, base date 31 March 2025.