Approved but held up · West Lothian

The Firs, Langside Gardens

Polbeth, West Lothian · EH55 8QX

ConstrainedHigh confidence

Homes

21

On the map, not added to the totals

Built so far

0

At the audit's base date, 31 March 2025

Still to build

21

council audit figure

Not a live consent, so it is not added to the homes total.
Holding it up: Developer states the site is not vialbe with section 75 contributions. Developer contributions are required..

Where it is

The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
private
Mix
21 flats

Planning

Reference
1260/FUL/21; 0598/PO/25
Decision
Full permission
Dated
12/06/2023; refused 29/9/25
Audit reference
353
Audit base date
31 March 2025

What the application says

Erection of 21 flats, access, parking, landscaping and associated works

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at The Firs, Langside Gardens
YearHomes
2026/2721
Programmed in total21

Where this comes from

West Lothian HLA 2025. In West Lothian Council Housing Land Audit 2025, base date 31 March 2025.