Skip to content

Building now · East Lothian

Hallhill Southwest Dunbar

Dunbar, East Lothian

Under constructionHigh confidence

Homes

240

Counted in the audit's total

Built so far

220

At the audit's base date, 31 March 2025

Still to build

20

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Mix
37 houses
Position
Matched to the planning register by reference

Planning

Reference
19/01162/P
Decision
Full
Dated
26 January 2012
Audit reference
E263
Audit base date
31 March 2025

What the application says

Approval of matters specified in conditions of planning permission in principle 09/00486/OUT- Erection of 240 houses and associated works

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Hallhill Southwest Dunbar
YearHomes
2025/268
2026/2712
Programmed in total20

Where this comes from

East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.

A home to sell before you buy?

A move to a new home in Dunbar starts with the one you own now: what it would sell for, or what it would let for if you kept it. Enter its postcode and the figure is on your screen.

Both are free and instant on screen. No email needed to see the number.