Approved, not started · West Lothian
Edinburgh Road
Linlithgow, West Lothian
ConsentedHigh confidence
Homes
18
Counted in the audit's total
Built so far
0
At the audit's base date, 31 March 2025
Still to build
18
council audit figure
Where it is
The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.
- Open in the atlas
- Google Maps
- OpenStreetMap
- 55.97702, -3.58876
About the site
- Builder
- CCG (Scotland) Ltd / Morrison Community Care Devco Ltd
- Mix
- 18 flats
Planning
- Reference
- 0201/FUL/18; 0580/FUL/23
- Decision
- Full permission
- Dated
- 02/08/2019; 06/02/2025
- Audit reference
- 278
- Audit base date
- 31 March 2025
Homes expected each year
The council’s own build-out programme. The first year is the current audit year.
| Year | Homes |
|---|---|
| 2026/27 | 18 |
| Programmed in total | 18 |
Where this comes from
West Lothian HLA 2025. In West Lothian Council Housing Land Audit 2025, base date 31 March 2025.
- Open the source record (westlothian.gov.uk)