Approved but held up · West Lothian

Broompark Farm

East Calder, West Lothian · EH53 0EB

ConstrainedHigh confidence

Homes

53

On the map, not added to the totals

Built so far

0

At the audit's base date, 31 March 2025

Still to build

53

council audit figure

Not a live consent, so it is not added to the homes total.
Holding it up: Conflicting feedback from landowners agent and HFS. HFS feedback is that the landowner is not willing to sell. Landowners agent feedback is that discussions with housebuilders are ongoing and it is not unreasonable to expect completion by the end of the 26/27 year. On balance it is considered that until a deal with a developer has happened it is doubtful the site will be brought forward given the lack of progress since allocation..

Where it is

The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Builder
Broompark Holdings Ltd
Site area
3.03 ha

Planning

Reference
0281/P/20
Decision
Permission in principle
Dated
6 June 2022
Audit reference
53
Plan reference
H-EC 3
Audit base date
31 March 2025

Where this comes from

West Lothian HLA 2025. In West Lothian Council Housing Land Audit 2025, base date 31 March 2025.

Buying into one of these, letting near one, or weighing the return.

A new estate in East Calder brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.