Blindwells Phase 1 (3AA/AB) (Plot 3)

Blindwells, East Lothian

Under constructionHigh confidence

Homes

167

Counted in the audit's total

Built so far

134

At the audit's base date, 31 March 2025

Still to build

33

council audit figure

Affordable

0

Within the total

Where it is

The pin is the record's own position on the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Position
Geocoded from the site name

Planning

Reference
21/00308/AMM
Decision
AMM
Dated
7 September 2021
Audit reference
E273a phase 1
Audit base date
31 March 2025

What the application says

Approval of matters specified in conditions of planning permission in principle 14/00768/PPM - Erection of 185 houses, 12 flats and associated works

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Blindwells Phase 1 (3AA/AB) (Plot 3)
YearHomes
2025/2633
Programmed in total33

Where this comes from

East Lothian Council Housing Land Audit 2025. In East Lothian Council Housing Land Audit 2025, base date 31 March 2025.