Almondell WBc/WBe/WBf (Taylor Wimpey)

East Calder, West Lothian · EH53 0

Also recorded as Calderwood.

Under constructionHigh confidence

Homes

366

Counted in the audit's total

Built so far

1

At the audit's base date, 31 March 2025

Still to build

365

council audit figure

Affordable

212

Within the total

Where it is

The site boundary is the council's own, drawn over the atlas. Scroll the page over the map; hold Ctrl to zoom it.

About the site

Tenure
private

Planning

Reference
0524/P/09
Decision
Full permission
Dated
15 March 2009
Audit reference
151
Plan reference
H-EC 9
Audit base date
31 March 2025

Notes

Housing Land Audit 2024; largest remaining Stirling parcel in Almondell.

Homes expected each year

The council’s own build-out programme. The first year is the current audit year.

Homes expected each year at Almondell WBc/WBe/WBf (Taylor Wimpey)
YearHomes
2027/2840
2028/29100
2029/30100
2030/3193
2031/3232
Programmed in total365

Where this comes from

West Lothian HLA 2025. In West Lothian Council Housing Land Audit 2025, base date 31 March 2025.

Buying into one of these, letting near one, or weighing the return.

A new estate in East Calder brings first owners who later move on and let, tenants who want a modern home near the same schools and stations, and a supply figure worth knowing before you buy. Tell us which you are and the right person calls you back.